Loading...
Way History: 200 (705587328)
Version #21
max speed
- Edited by infrastructure
- Changeset #143843248
Tags
construction:railway:etcs | 2 |
---|---|
electrified | contact_line |
frequency | 50 |
gauge | 1435 |
maxspeed | 150 |
name | 200 |
passenger_lines | 2 |
railway | rail |
railway:etcs | no |
railway:gnt | no |
railway:lzb | no |
railway:pzb | yes |
start_date | 2020 |
status | AC,builder:ASTALDI+FCC+SALCEF+THALES,progress_estimate:100%/01.10.2020 |
usage | main |
voltage | 25000 |
Nodes
17 nodes
- 6629692418 (part of way 200 (705587327))
- 7882023658
- 7882023660
- 7347091183
- 7882023662
- 7882023663
- 6629692416
- 7882023666
- 6629692415
- 7347091181
- 7882023668
- 6629692414
- 7882023670
- 6629692413
- 7881861112
- 9004438029 (part of way 677273732)
- 6341654584 (part of ways 705587324 and 200 (1011343590))
Version #20
Updated old, replaced track near Ghioroc: catenary poles are still in place so abandoned is more appropriate
Tags
construction:railway:etcs | 2 |
---|---|
electrified | contact_line |
frequency | 50 |
gauge | 1435 |
maxspeed | 160 |
name | 200 |
passenger_lines | 2 |
railway | rail |
railway:etcs | no |
railway:gnt | no |
railway:lzb | no |
railway:pzb | yes |
start_date | 2020 |
status | AC,builder:ASTALDI+FCC+SALCEF+THALES,progress_estimate:100%/01.10.2020 |
usage | main |
voltage | 25000 |
Nodes
17 nodes
- 6629692418 (part of way 200 (705587327))
- 7882023658
- 7882023660
- 7347091183
- 7882023662
- 7882023663
- 6629692416
- 7882023666
- 6629692415
- 7347091181
- 7882023668
- 6629692414
- 7882023670
- 6629692413
- 7881861112
- 9004438029 (part of way 677273732)
- 6341654584 (part of ways 705587324 and 200 (1011343590))
Version #19
corrected
- Edited by RobertH-PUM
- Changeset #103018631
Tags
construction:railway:etcs | 2 |
---|---|
electrified | contact_line |
frequency | 50 |
gauge | 1435 |
maxspeed | 160 |
name | 200 |
passenger_lines | 2 |
railway | rail |
railway:etcs | no |
railway:gnt | no |
railway:lzb | no |
railway:pzb | yes |
start_date | 2020 |
status | AC,builder:ASTALDI+FCC+SALCEF+THALES,progress_estimate:100%/01.10.2020 |
usage | main |
voltage | 25000 |
Nodes
16 nodes
- 6629692418 (part of way 200 (705587327))
- 7882023658
- 7882023660
- 7347091183
- 7882023662
- 7882023663
- 6629692416
- 7882023666
- 6629692415
- 7347091181
- 7882023668
- 6629692414
- 7882023670
- 6629692413
- 7881861112
- 6341654584 (part of ways 705587324 and 200 (1011343590))
Version #18
Fixing Section 200
- Edited by RobertH-PUM
- Changeset #100271068
Tags
construction:railway:etcs | 2 |
---|---|
electrified | contact_line |
frequency | 50 |
gauge | 1435 |
maxspeed | 160 |
name | 200 |
railway | rail |
start_date | 2020 |
status | AC,builder:ASTALDI+FCC+SALCEF+THALES,progress_estimate:100%/01.10.2020 |
usage | main |
voltage | 25000 |
Nodes
16 nodes
- 6629692418 (part of way 200 (705587327))
- 7882023658
- 7882023660
- 7347091183
- 7882023662
- 7882023663
- 6629692416
- 7882023666
- 6629692415
- 7347091181
- 7882023668
- 6629692414
- 7882023670
- 6629692413
- 7881861112
- 6341654584 (part of ways 705587324 and 200 (1011343590))
Version #17
corrected
- Edited by RobertH-PUM
- Changeset #96117066
Tags
construction:railway:etcs | 2 |
---|---|
electrified | contact_line |
frequency | 50 |
maxspeed | 160 |
name | Varianta Ghiroc |
railway | rail |
start_date | 2020 |
status | AC,builder:ASTALDI+FCC+SALCEF+THALES,progress_estimate:100%/01.10.2020 |
usage | main |
voltage | 25000 |
Nodes
16 nodes
- 6629692418 (part of way 200 (705587327))
- 7882023658
- 7882023660
- 7347091183
- 7882023662
- 7882023663
- 6629692416
- 7882023666
- 6629692415
- 7347091181
- 7882023668
- 6629692414
- 7882023670
- 6629692413
- 7881861112
- 6341654584 (part of ways 705587324 and 200 (1011343590))
Version #16
update status
- Edited by RobertH-PUM
- Changeset #94398403
Tags
construction:railway:etcs | 2 |
---|---|
electrified | contact_line |
frequency | 50 |
maxspeed | 160 |
name | Reabilitare M200 varianta (km614-Ghiroc) |
operator | CFR |
railway | rail |
start_date | 2020 |
status | AC,builder:ASTALDI+FCC+SALCEF+THALES,progress_estimate:100%/01.10.2020 |
usage | main |
voltage | 25000 |
Nodes
16 nodes
- 6629692418 (part of way 200 (705587327))
- 7882023658
- 7882023660
- 7347091183
- 7882023662
- 7882023663
- 6629692416
- 7882023666
- 6629692415
- 7347091181
- 7882023668
- 6629692414
- 7882023670
- 6629692413
- 7881861112
- 6341654584 (part of ways 705587324 and 200 (1011343590))
Version #15
railway done
- Edited by RobertH-PUM
- Changeset #92606548
Tags
construction:railway:etcs | 2 |
---|---|
electrified | contact_line |
frequency | 50 |
maxspeed | 160 |
name | Reabilitare M200 varianta (km614-Ghiroc) |
operator | CFR |
railway | rail |
start_date | 2020 |
status | AC,builder:ASTALDI+FCC+SALCEF+THALES,progress:100%/01.10.2020 |
usage | main |
voltage | 25000 |
Nodes
16 nodes
- 6629692418 (part of way 200 (705587327))
- 7882023658
- 7882023660
- 7347091183
- 7882023662
- 7882023663
- 6629692416
- 7882023666
- 6629692415
- 7347091181
- 7882023668
- 6629692414
- 7882023670
- 6629692413
- 7881861112
- 6341654584 (part of ways 705587324 and 200 (1011343590))
Version #14
corrected geometry
- Edited by RobertH-PUM
- Changeset #90493216
Tags
construction:electrified | contact_line |
---|---|
construction:frequency | 50 |
construction:railway | rail |
construction:railway:etcs | 2 |
construction:voltage | 25000 |
maxspeed | 160 |
name | Reabilitare M200 varianta (km614-Ghiroc) |
operator | CFR |
railway | construction |
source | http://www.cfr.ro/files/doclic/ReabilitareCurticiSimeria2a-2b/TR.2-A_1/Lot%202/PODURI/desene/PLAN%20DE%20INCADRARE%20IN%20ZONA%20KM%20608+999.pdf |
status | AC,builder:ASTALDI+FCC+SALCEF+THALES,progress:45.5%/18.08.2020 42.25%/03.07.2020 38.5%/17.01.2020 7.81%/18.02.2019 |
usage | main |
Nodes
16 nodes
- 6629692418 (part of way 200 (705587327))
- 7882023658
- 7882023660
- 7347091183
- 7882023662
- 7882023663
- 6629692416
- 7882023666
- 6629692415
- 7347091181
- 7882023668
- 6629692414
- 7882023670
- 6629692413
- 7881861112
- 6341654584 (part of ways 705587324 and 200 (1011343590))
Version #13
corrected geometry
- Edited by RobertH-PUM
- Changeset #90491896
Tags
construction:electrified | contact_line |
---|---|
construction:frequency | 50 |
construction:railway | rail |
construction:railway:etcs | 2 |
construction:voltage | 25000 |
maxspeed | 160 |
name | Reabilitare M200 varianta (km614-Ghiroc) |
operator | CFR |
railway | construction |
source | http://www.cfr.ro/files/doclic/ReabilitareCurticiSimeria2a-2b/TR.2-A_1/Lot%202/PODURI/desene/PLAN%20DE%20INCADRARE%20IN%20ZONA%20KM%20608+999.pdf |
status | AC,builder:ASTALDI+FCC+SALCEF+THALES,progress:45.5%/18.08.2020 42.25%/03.07.2020 38.5%/17.01.2020 7.81%/18.02.2019 |
usage | main |
Nodes
9 nodes
- 6629692418 (part of way 200 (705587327))
- 7347091183
- 6629692416
- 6629692415
- 7347091181
- 6629692414
- 6629692413
- 7881861112
- 6341654584 (part of ways 705587324 and 200 (1011343590))
Version #12
update progress
- Edited by RobertH-PUM
- Changeset #89586167
Tags
construction:electrified | contact_line |
---|---|
construction:frequency | 50 |
construction:railway | rail |
construction:railway:etcs | 2 |
construction:voltage | 25000 |
maxspeed | 160 |
name | Reabilitare M200 varianta (km614-Ghiroc) |
operator | CFR |
railway | construction |
source | http://www.cfr.ro/files/doclic/ReabilitareCurticiSimeria2a-2b/TR.2-A_1/Lot%202/PODURI/desene/PLAN%20DE%20INCADRARE%20IN%20ZONA%20KM%20608+999.pdf |
status | AC,builder:ASTALDI+FCC+SALCEF+THALES,progress:45.5%/18.08.2020 42.25%/03.07.2020 38.5%/17.01.2020 7.81%/18.02.2019 |
usage | main |
Nodes
8 nodes
- 6629692418 (part of way 200 (705587327))
- 7347091183
- 6629692416
- 6629692415
- 7347091181
- 6629692414
- 6629692413
- 6341654584 (part of ways 705587324 and 200 (1011343590))
Version #11
update status
- Edited by RobertH-PUM
- Changeset #87505373
Tags
construction:electrified | contact_line |
---|---|
construction:frequency | 50 |
construction:railway | rail |
construction:railway:etcs | 2 |
construction:voltage | 25000 |
maxspeed | 160 |
name | Reabilitare M200 varianta (km614-Ghiroc) |
operator | CFR |
railway | construction |
source | http://www.cfr.ro/files/doclic/ReabilitareCurticiSimeria2a-2b/TR.2-A_1/Lot%202/PODURI/desene/PLAN%20DE%20INCADRARE%20IN%20ZONA%20KM%20608+999.pdf |
status | AC,builder:ASTALDI+FCC+SALCEF+THALES,progress:42.25%/03.07.2020 41.55%/18.05.2020 39.4%/28.02.2020 38.5%/17.01.2020 7.81%/18.02.2019 |
usage | main |
Nodes
8 nodes
- 6629692418 (part of way 200 (705587327))
- 7347091183
- 6629692416
- 6629692415
- 7347091181
- 6629692414
- 6629692413
- 6341654584 (part of ways 705587324 and 200 (1011343590))
Version #10
added keys
- Edited by home_in_the_distance
- Changeset #87201044
Tags
construction:electrified | contact_line |
---|---|
construction:frequency | 50 |
construction:railway | rail |
construction:railway:etcs | 2 |
construction:voltage | 25000 |
maxspeed | 160 |
name | Reabilitare M200 varianta (km614-Ghiroc) |
operator | CFR |
railway | construction |
source | http://www.cfr.ro/files/doclic/ReabilitareCurticiSimeria2a-2b/TR.2-A_1/Lot%202/PODURI/desene/PLAN%20DE%20INCADRARE%20IN%20ZONA%20KM%20608+999.pdf |
status | AC,builder:ASTALDI+FCC+SALCEF+THALES,progress:41.55%/18.05.2020 39.4%/28.02.2020 38.5%/17.01.2020 7.81%/18.02.2019 |
usage | main |
Nodes
8 nodes
- 6629692418 (part of way 200 (705587327))
- 7347091183
- 6629692416
- 6629692415
- 7347091181
- 6629692414
- 6629692413
- 6341654584 (part of ways 705587324 and 200 (1011343590))
Version #9
update status
- Edited by RobertH-PUM
- Changeset #85389993
Tags
construction:railway:etcs | 2 |
---|---|
maxspeed | 160 |
name | Reabilitare M200 varianta (km614-Ghiroc) |
railway | construction |
source | http://www.cfr.ro/files/doclic/ReabilitareCurticiSimeria2a-2b/TR.2-A_1/Lot%202/PODURI/desene/PLAN%20DE%20INCADRARE%20IN%20ZONA%20KM%20608+999.pdf |
status | AC,builder:ASTALDI+FCC+SALCEF+THALES,progress:41.55%/18.05.2020 39.4%/28.02.2020 38.5%/17.01.2020 7.81%/18.02.2019 |
Nodes
8 nodes
- 6629692418 (part of way 200 (705587327))
- 7347091183
- 6629692416
- 6629692415
- 7347091181
- 6629692414
- 6629692413
- 6341654584 (part of ways 705587324 and 200 (1011343590))
Version #8
update
- Edited by RobertH-PUM
- Changeset #82837052
Tags
construction:railway:etcs | 2 |
---|---|
maxspeed | 160 |
name | Reabilitare M200 varianta (km614-Ghiroc) |
railway | construction |
source | http://www.cfr.ro/files/doclic/ReabilitareCurticiSimeria2a-2b/TR.2-A_1/Lot%202/PODURI/desene/PLAN%20DE%20INCADRARE%20IN%20ZONA%20KM%20608+999.pdf |
status | AC,builder:ASTALDI+FCC+SALCEF+THALES,progress:39.4%/28.02.2020 38.5%/17.01.2020 31.6%/18.10.2019 29.1%/17.09.2019 27.1%/28.08.2019 11.76%/18.06.2019 8.93%/14.05.2019 7.81%/18.02.2019 |
Nodes
8 nodes
- 6629692418 (part of way 200 (705587327))
- 7347091183
- 6629692416
- 6629692415
- 7347091181
- 6629692414
- 6629692413
- 6341654584 (part of ways 705587324 and 200 (1011343590))
Version #7
Update status
- Edited by RobertH-PUM
- Changeset #81926405
Tags
construction:railway:etcs | 2 |
---|---|
maxspeed | 160 |
name | Reabilitare M200 varianta (km614-Ghiroc) |
railway | construction |
source | http://www.cfr.ro/files/doclic/ReabilitareCurticiSimeria2a-2b/TR.2-A_1/Lot%202/PODURI/desene/PLAN%20DE%20INCADRARE%20IN%20ZONA%20KM%20608+999.pdf |
status | AC,builder:ASTALDI+FCC+SALCEF+THALES,progress:39.4%/28.02.2020 38.5%/17.01.2020 31.6%/18.10.2019 29.1%/17.09.2019 27.1%/28.08.2019 11.76%/18.06.2019 8.93%/14.05.2019 7.81%/18.02.2019 |
Nodes
7 nodes
Version #6
Update status
- Edited by RobertH-PUM
- Changeset #79744785
Tags
construction:railway:etcs | 2 |
---|---|
maxspeed | 160 |
name | Reabilitare M200 varianta (km614-Ghiroc) |
railway | construction |
source | http://www.cfr.ro/files/doclic/ReabilitareCurticiSimeria2a-2b/TR.2-A_1/Lot%202/PODURI/desene/PLAN%20DE%20INCADRARE%20IN%20ZONA%20KM%20608+999.pdf |
status | AC,builder:ASTALDI+FCC+SALCEF+THALES,progress:38.5%/17.01.2020 31.6%/18.10.2019 29.1%/17.09.2019 27.1%/28.08.2019 11.76%/18.06.2019 8.93%/14.05.2019 7.81%/18.02.2019 |
Nodes
7 nodes
Version #5
ETCS planned to implement
- Edited by RobertH-PUM
- Changeset #76219623
Tags
construction:railway:etcs | 2 |
---|---|
maxspeed | 160 |
name | Reabilitare M200 varianta (km614-Ghiroc) |
railway | construction |
source | http://www.cfr.ro/files/doclic/ReabilitareCurticiSimeria2a-2b/TR.2-A_1/Lot%202/PODURI/desene/PLAN%20DE%20INCADRARE%20IN%20ZONA%20KM%20608+999.pdf |
status | AC,builder:ASTALDI+FCC+SALCEF+THALES,progress:31.6%/18.10.2019 29.1%/17.09.2019 27.1%/28.08.2019 11.76%/18.06.2019 8.93%/14.05.2019 7.81%/18.02.2019 |
Nodes
7 nodes
Version #4
Update status
- Edited by RobertH-PUM
- Changeset #76152122
Tags
maxspeed | 160 |
---|---|
name | Reabilitare M200 varianta (km614-Ghiroc) |
railway | construction |
source | http://www.cfr.ro/files/doclic/ReabilitareCurticiSimeria2a-2b/TR.2-A_1/Lot%202/PODURI/desene/PLAN%20DE%20INCADRARE%20IN%20ZONA%20KM%20608+999.pdf |
status | AC,builder:ASTALDI+FCC+SALCEF+THALES,progress:31.6%/18.10.2019 29.1%/17.09.2019 27.1%/28.08.2019 11.76%/18.06.2019 8.93%/14.05.2019 7.81%/18.02.2019 |
Nodes
7 nodes
Version #3
Status update
- Edited by RobertH-PUM
- Changeset #74590096
Tags
maxspeed | 160 |
---|---|
name | Reabilitare M200 varianta (km614-Ghiroc) |
railway | construction |
source | http://www.cfr.ro/files/doclic/ReabilitareCurticiSimeria2a-2b/TR.2-A_1/Lot%202/PODURI/desene/PLAN%20DE%20INCADRARE%20IN%20ZONA%20KM%20608+999.pdf |
status | AC,builder:ASTALDI+FCC+SALCEF+THALES,progress:29.1%/17.09.2019 27.1%/28.08.2019 11.76%/18.06.2019 8.93%/14.05.2019 7.81%/18.02.2019 |
Nodes
7 nodes
Version #2
Update status
- Edited by RobertH-PUM
- Changeset #73848741
Tags
maxspeed | 160 |
---|---|
name | Reabilitare M200 varianta (km614-Ghiroc) |
railway | construction |
source | http://www.cfr.ro/files/doclic/ReabilitareCurticiSimeria2a-2b/TR.2-A_1/Lot%202/PODURI/desene/PLAN%20DE%20INCADRARE%20IN%20ZONA%20KM%20608+999.pdf |
status | AC,builder:ASTALDI+FCC+SALCEF+THALES,progress:27.1%/28.08.2019 11.76%/18.06.2019 8.93%/14.05.2019 7.81%/18.02.2019 |
Nodes
7 nodes
Version #1
Corrected location of POI
- Edited by RobertH-PUM
- Changeset #72405532
Tags
maxspeed | 160 |
---|---|
name | Reabilitare M200 varianta (km614-Ghiroc) |
railway | construction |
source | http://www.cfr.ro/files/doclic/ReabilitareCurticiSimeria2a-2b/TR.2-A_1/Lot%202/PODURI/desene/PLAN%20DE%20INCADRARE%20IN%20ZONA%20KM%20608+999.pdf |
status | AC,builder:ASTALDI+FCC+SALCEF+THALES,progress:11.76%/18.06.2019 8.93%/14.05.2019 7.81%/18.02.2019 |
Nodes
7 nodes
Welcome to OpenStreetMap!
OpenStreetMap is a map of the world, created by people like you and free to use under an open license.
Hosting is supported by Fastly, OSMF corporate members, and other partners.
https://openstreetmap.org/copyright | https://openstreetmap.org |
Copyright OpenStreetMap and contributors, under an open license |